RE Cinco Gen-Tie Project Compliance Management

OVERVIEW

Serving as an extension of staff for the United State Bureau of Land Management (BLM), EGI is currently providing environmental compliance oversight for the Recurrent Energy Cinco Gen-Tie Project. The Project consists of construction of an approximately 260 kilovolt transmission generation tie-in. The Gen-Tie extends approximately two miles from a 60 megawatt solar photovoltaic power generation facility on private land to the Los Angeles Department of Water and Power (LADWP) Barren Ridge Switch Yard. EGI’s duties include oversight of contractors and environmental monitors. EGI will also work closely with the BLM and other regulatory agencies such as the United States Fish and Wildlife Service. EGI will prepare reports on a regular basis to document progress and any violations of required protocols.

DETAILS

Client

Recurrent Energy

Date

In Progress

Service

Mitigation Monitoring

RELATED PROJECTS